Main Civil Works for GLMRF, Mundra Gujarat

The Main Civil Work for GLMRF project at Mundra, Gujarat was a significant project for VRC Constructions India Ltd. The project was executed under the supervision of Toyo Engineering India Pvt. Ltd. The total budget allocated for this project was 48.46 crores, which was used efficiently to complete the project to the highest standards.

The project began on 29th September 2014 and was completed within the specified timeframe on 29th March 2017. The team at VRC Construction, a reputed civil contractor in India, worked hard to ensure that all the work was completed to the highest standards, within the budget, and on time. They used their experience, skills, and knowledge to complete the project, which was a testament to their commitment and dedication to delivering quality work.

The Main Civil Work for GLMRF project was a complex project that required a high level of expertise and experience. The team at VRC Constructions India Ltd., one of the best civil contractor in India, was well-equipped to handle the challenges and was able to complete the project to the satisfaction of all stakeholders. The successful completion of this project is a testament to the company’s commitment to delivering quality work and its ability to execute complex projects efficiently and effectively.

 

Name of the Project Main Civil Works for GLMRF, Mundra Gujarat
Name of the Client Toyo Engineering India Pvt. Ltd.
Work Executed By VRC Constructions India Ltd.
Location Gujarat
Construction Cost (in INR) 48.46 Crore
Segment Civil Construction
Sector Public
Construction Start Date 29.09.2014
Construction Completion Date 29.03.2017
Latest Status Completed